Cost

Cost Performance Index (CPI)

DE: Kostenleistungsindex (CPI)

A measure of cost efficiency expressed as EV / AC.

Detailed Explanation

CPI measures cost efficiency as the ratio of earned value to actual cost (CPI = EV / AC). It is the most critical EVM metric for assessing whether a project is getting value for its spending.

CPI of 1.0 = on budget; >1.0 = under budget (favorable); <1.0 = over budget. Research shows that once CPI falls below 0.8 after 20% completion, recovery is extremely unlikely.

CPI is used in forecasting: EAC = BAC / CPI assumes current cost efficiency continues. This makes CPI invaluable for early warning and proactive corrective action.

Key Points

  • Formula: CPI = EV / AC
  • 1.0 = on budget; >1.0 under; <1.0 over
  • Most important EVM cost indicator
  • Below 0.8 at 20% completion rarely recovers
  • Used in EAC forecasting: EAC = BAC / CPI
  • Track alongside SPI for complete health picture

Practical Example

At month 4 of a EUR 500K project: EV = EUR 120K, AC = EUR 150K. CPI = 0.80 — for every euro spent, only 80 cents of value is earned. EAC = 500K / 0.80 = EUR 625K, a potential EUR 125K overrun. The PM investigates: inefficient vendor contracts and rework from unclear requirements.

Tips for Learning and Applying

1

Track CPI weekly during execution

2

If CPI drops below 0.90, investigate immediately

3

Use both cumulative and period CPI to distinguish trends from one-time events

4

Always report CPI alongside SPI

Want to Master These Concepts?

Our courses cover all these terms in depth with practical examples and exercises.