Schedule

Three-Point Estimate

DE: Drei-Punkt-Schaetzung

Using optimistic, most likely, and pessimistic values to estimate duration or cost.

Detailed Explanation

Three-point estimating uses three values — optimistic (O), most likely (M), and pessimistic (P) — to define an approximate range for an activity's cost or duration. Two common formulas are: PERT weighted average (O + 4M + P) / 6, and simple average (O + M + P) / 3.

This technique accounts for estimation uncertainty by producing a range rather than a single number. The PERT formula gives the most likely estimate 4x the weight of the extremes, producing a more moderate result that accounts for the common tendency toward the most likely outcome.

Three-point estimates also enable calculation of standard deviation = (P - O) / 6, which quantifies the uncertainty. Combined with probability theory, this allows PMs to express confidence levels: the estimate plus one standard deviation gives approximately 84% confidence.

Key Points

  • Three values: Optimistic (O), Most Likely (M), Pessimistic (P)
  • PERT formula: (O + 4M + P) / 6
  • Simple average: (O + M + P) / 3
  • Standard deviation: (P - O) / 6
  • Provides range with confidence levels, not false precision
  • Input for PERT analysis and Monte Carlo simulation

Practical Example

Estimating website development: O = 8 weeks, M = 12 weeks, P = 22 weeks. PERT = (8 + 48 + 22) / 6 = 13 weeks. SD = (22 - 8) / 6 = 2.3 weeks. The PM presents: '13 weeks expected, with 84% confidence of finishing within 15.3 weeks.' This transparent range is more useful than a single-point '12 weeks' estimate.

Tips for Learning and Applying

1

Get honest estimates — especially pessimistic ones, which people tend to understate

2

Use PERT for higher accuracy; simple average for quick estimates

3

Present ranges with confidence levels to stakeholders

4

Combine with Monte Carlo for project-level analysis

Want to Master These Concepts?

Our courses cover all these terms in depth with practical examples and exercises.